Client: Klinikum der Universität München vertreten durch das Staatliche Bauamt München 2
Planning Period: 03/2022 - 12/2023
Construction Period: 12/2023 - 04/2025
Cost of construction: ca. 1,1 Mio. €
LPH 3, 5-9
Project team: Alejandro Marak, Debora Kahan, Sude Eskicioglu
Modernization of ward H4 at Großhadern Hospital
On the grounds of the University of Munich Hospital Großhadern, ward H4 is being refurbished and visually upgraded. The measure includes beautification work within the ward, dismantling of old facilities from the 1975 construction period and adjustments to fire protection. The construction work will be carried out while the hospital is in operation and will be separated by dust protection walls.