General refurbishment of the H2 intensive care unit at Großhadern Hospital
Client:
Freistaat Bayern vertreten durch das Staatliche Bauamt München 2
Planning period: 02/2021 - 09/2021
Construction period: 09/2021 - ca. 03/2025
Cost of construction: ca. 5,4 Mio. €
BGF ca. 977 m²
LPH 3, 5-9
Project team: Lida Papakyriakopoulou, Alejandro Marak, Debora Kahan
construction management: Marianne Dechant, Sicco Schmidt
General refurbishment of the H2 intensive care unit at Großhadern Hospital
Ward H2 is being refurbished and updated for use as an intensive care unit. The refurbishment measures concern the functional optimisation of the room structures in the process flow of intensive care, dismantling of the existing facilities, renewal of the windows, adaptation of the fire protection and the visual upgrading of the ward.
The measures will be carried out while the neighbouring hospital areas continue to operate.
Client:
Freistaat Bayern vertreten durch das Staatliche Bauamt München 2
Planning period: 02/2021 - 09/2021
Construction period: 09/2021 - ca. 03/2025
Cost of construction: ca. 5,4 Mio. €
BGF ca. 977 m²
LPH 3, 5-9
Project team: Lida Papakyriakopoulou, Alejandro Marak, Debora Kahan
construction management: Marianne Dechant, Sicco Schmidt